#1  
29th January 2022, 04:55 PM
Souvik Saha 8420
 
Join Date: Jan 2022
Posts: 1

Calculate works cost for the given worker


Standard time taken to produce one unit is 48 seconds. Hourly rate is Rs. 150. In an 8 hours day a worker produced 700 units and additionally they will get DA @ 20% of piece wages and travelling allowance of Rs. 320. For a particular job material required for Rs. 2000 and factory overhead for Rs. 1000. 4x2=8 Calculate works cost for that worker.




Do you have any question? or have anything to say?





Powered by vBulletin® Version 3.8.3
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Search Engine Optimization by vBSEO 3.3.0
Please also check: